Crews in Stillwater are working to repair streets and city-owned parking lots impacted by a sinkhole that appeared last month after the collapse of an 1887 brick sewer tunnel near the Stillwater Veterans Memorial at Third and Pine streets.
Officials say the repairs should be complete in time for this year’s Memorial Day service at the memorial.
“We are optimistic it’ll all be taken care of by then,” said Stillwater Veterans Memorial Chairwoman Rachael Kozlowski. “As you know we have the best mayor in all of Minnesota, and I know the city is working hard to get this fixed well and quickly.”
Kozlowski is married to Stillwater Mayor Ted Kozlowski.
The sinkhole was discovered during the early morning hours of April 27 on Cub’s corporate property in the city’s utility easement, according to Elizabeth Bechel, the city’s administrative services director.The sinkhole created a void approximately 25 feet below ground, she said.
A temporary sewer bypass was installed while the tunnel was filled with flowable concrete and a new sewer connection is being built on Pine Street between Third and Fourth streets.
The repairs impacted the Teddy Bear Park parking lot, the Cub parking lot, and both the upper and lower Veterans Memorial parking areas. Work has also affected portions of Second Street, Third Street, Fourth Street, Pine Street, Oak Street and Olive Street.
Although most work should be complete by Memorial Day, follow-up work items will continue throughout May and June, but with less impact to residents and visitors, Bechel said.
City officials learned of the sewer collapse from staff at the Metropolitan Council Environmental Services Wastewater Treatment Plant, said Shawn Sanders, the city’s director of public works.
“They said, ‘Hey, we’ve gotten a lot of sediment down in our wastewater treatment plant. You guys might want to check out your system,’” Sanders said. “So we had to do a little backtracking and kind of trace to where it was and then we found it.”
Crews examined the city’s current sewer system and were able to “reroute it to a different sewer main system, so we’re not using the same location as before,” Sanders said. He estimated the emergency repairs will cost around $500,000.
The Memorial Day service, which will be at 11:30 a.m. May 25, will honor veterans from the St. Croix River Valley who died serving their country.
The featured speaker will be retired U.S. Navy Explosive Ordnance Disposal Chief Nichole M. Kelly. Kelly graduated from Central High School in St. Paul and was a Division I hockey goalie at the University of Findlay in Ohio.
Kelly served one tour in Afghanistan and worked as a Basic Underwater Demolition/SEAL instructor at the Naval Special Warfare Training Center in Coronado, Calif. When she retired this month, she was one of only two female explosive ordnance disposal Chiefs in the Navy.
The ceremony also will include music by the Croix Chordsmen and the Stillwater Area High School band.
A flag raising and flyover by the T-6 Thunder Flight Team is planned for noon.
While some seating will be provided, attendees are encouraged to bring their own lawn chairs. For more information, go to stillwaterveteransmemorial.org.