10 Mile Road
10 Mile Road between Ryan Road and Lorraine Avenue in Warren and Center Line. One lane of traffic will be maintained in each direction. Turning movements from 10 Mile Road onto intersecting roads will be restricted at times with flagging operations in place. A full closure will take place at the railroad crossing for approximately 35 days during reconstruction operations. Project consists of road rehabilitation between Ryan Road and Sherwood Avenue and road reconstruction between Sherwood Avenue and Lorraine Avenue. Drivers are encouraged to follow posted detours and seek alternate routes when possible. Project duration through November.
34 Mile Road Bridge
34 Mile Road Bridge over Highbank Creek between Armada Ridge Road and Russ Road. 34 Mile Road will be closed to thru traffic between Armada Ridge Road and Russ Road due to bridge replacement. Drivers are encouraged to follow posted detours and seek alternate routes when possible. Project duration is through August.
Clinton River Trail
Due to a washout on the Clinton River Trail in Rochester, the trail has been closed west of the Macomb Orchard Trail and Dequindre Road. Follow the posted detour route.
Dequindre Road, Shelby Twp.
The Great Lakes Water Authority (GLWA) is continuing to work on the second phase of infrastructure improvements in the area of Dequindre Road between Hamlin Road and Avon Road and Dequindre Road between 23 Mile Road and 24 Mile Road is expected to be closed through fall. The Clinton River Trail and Macomb Orchard Trail between Letica Drive and 24 Mile Road will be closed. Drivers are encouraged to follow the posted detours and seek alternate routes when possible. Project consists of installation of new 96-inch water transmission main and is part of GLWA project. Project duration through Dec. 31.
Garfield Road
Garfield Road between 14 Mile Road and 15 Mile Road in Fraser. Northbound traffic will be maintained on the southbound lanes of Garfield Road. Southbound traffic on Garfield Road will be detoured to Utica Road. The eastbound right turn lane and westbound left turn lane of 15 Mile Road will be closed at Garfield Road. The westbound left turn lane from Klein Road to Garfield Road will be closed. Drivers are encouraged to follow the posted detours and seek alternate routes when possible. Project consists of road reconstruction and duration is through August.
South River Road Bridge
South River Road Bridge over the channel to Lake St. Clair east of Lakeshore Drive in Harrison Township. South River Road will remain open to traffic. A temporary bridge structure will be in place. Project consists of bridge replacement. Project duration will be through August.
I-275
In Wayne County, northbound I-275 ramp to westbound M-14 will be closed for construction through November 15.
I-696
In Oakland County, westbound I-696 from Farmington Road to Halsted Road will have two lanes open from 9 a.m.-3 p.m. Saturday for sign installation.
In Oakland County, westbound I-696 from M-10 to Telegraph Road will have two lanes open from 7 a.m. Monday until April 2 for slope restoration ect.
Eastbound I-696 will be closed from M-10 to I-75 for road reconstruction through November 15, 2026.
I-75
In Oakland County, northbound Dixie Highway/Saginaw Road ramp to I-75 will be closed from 7 a.m. Monday until early November for construction.
In Oakland County, eastbound and westbound East Holly ramp to northbound I-75 will be closed from 7 a.m. Monday until early November for construction.
In Wayne County, northbound I-75 ramp to I-94 will be closed from 9-10:30 a.m. Saturday for freeway cleaning.
In Wayne County, northbound I-75 ramp to westbound M-8/Davison will be closed from 10:30 a.m.-noon Saturday for freeway cleaning.
In Wayne County, northbound I-75 Service Drive at 8 Mile Road will have three lanes open from 7 a.m. Friday until early April for pump station work.
I-75 from M-15 to Genesee county line will have two lanes open until 7 p.m. Nov. 3.
I-94
In Wayne County, eastbound I-94 will have two lanes open from Middlebelt to Ecorse from 9 a.m.-3 p.m. daily through May 4 for median utility work.
In Wayne County, westbound I-94 will be closed intermittently from US-24/Telegraph to Middlebelt from 6-10 a.m. Sunday for cable crossing.
In Macomb County, westbound I-94 at 9 Mile Road will have one lane open from 9 a.m.-noon Saturday then two lanes open from noon-4 p.m. Saturday for bridge inspection.
In Wayne County, westbound I-94 ramp to southbound I-275 will be closed from 9 a.m. Monday until 5 a.m. Wednesday for drainage maintenance.
In Wayne County, eastbound I-94 will have two lanes open from Middlebelt to Inkster from 7 a.m.-5 p.m. Saturday and 5 a.m.-2 p.m. Sunday for median work.
M-8 (Davison)
In Wayne County, eastbound M-8 ramp to southbound M-10 will be closed from 1-2:30 p.m. Saturday for freeway cleaning.
M-10 (Lodge)
In Oakland County, southbound M-10 at 8 Mile Road will have two lanes open from 6 a.m. Monday until 6 pm. April 6 for retaining wall.
In Oakand County, northbound and southbound Greenfield ramp to southbound M-10 will be closed from 6 a.m. Monday until early April for retaining wall.
In Oakland County, southbound M-10 Service Drive from 8 Mile Road to Seven Mile Road will have one lane open from 6 a.m. Monday until early April for retaining wall.
In Wayne County, southbound M-10 ramp to Larned will be closed until late May for bridge work.
M-14/I-96
In Wayne County, eastbound M-14/I-96 will have one lane open from Sheldon to Newburgh until September for bridge rehabilitation and road and ramp reconstruction.
M-85 (Fort Street)
In Wayne County, eastbound and westbound M-85 will have one lane open at Livernois Avenue from 9 a.m.-3 p.m. until late April for utility/lighting work.
M-102 (8 Mile Road)
In Oakland and Wayne counties, westbound M-102 will have two lanes open from Southfield Road to Lahser Road until June.
US-12 (Michigann)
In Wayne County, westbound US-12 will have one lane open from Beech Daly to Middlebelt until 5 p.m. April 5 for water main work.
— MediaNews Group staff